Rebar for the beams and the beginnings of the ceiling formwork

I feel like a broken record, but I’m going to say it anyway. Even after the team from Hudson left, the following two weeks were still chaotic. I’m sure you’re not surprised. More surprising would be if I actually said that a week was calm and relaxed. Ha! If there is such a thing as a calm week here, I have yet to experience it.

The Hudson team left on a Saturday night, and by Monday, we were already planning for the next team, coming just two weeks later. It seemed like an early start, considering we started planning for Hudson about three days before they came, but we had much more to figure out this time. This team was bringing electricians with them! We were all super excited about this, but probably no one more than I was. It’s nice to have people around who speak the same language (in this case, I’m referring to the language of electricity… hehe), especially because I’ve been trying to troubleshoot some problems, and it’s hard to do that without anyone to bounce ideas off of.

On top of that, we had a looong list of electrical projects for them to work on. It’s always exciting when people with very useful skills come, and we do our best to take advantage of their knowledge and abilities while they’re here. That meant that I had to do a lot of planning to make sure that they could work efficiently, like making diagrams showing what we wanted, figuring out how/where lights should be installed, and buying the equipment and supplies we needed to be prepared.

Besides the electrical stuff, we had a bunch of other mostly finished projects that needed to be completely finished sooner rather than later… so we were hoping that the team could get them done. Practically, I think that smaller teams are better because everyone can really get to know each other. When I’m puzzling over how we can possibly finish everything that we need to during a team week, I wish that every team had 40 people.

Sesame seed-covered cookie
Debbie and I were out shopping for supplies, and I smelled something amazing… usually the air smells like garbage, so this was an especially welcome change. I followed my nose to a little, hole-in-the-wall bakery, and Debbie asked what smelled so good. I had my doubts when the woman pointed to this cookie, but it was SO GOOD. Moral of the story: trust your nose.

Aside from the planning work, there was some extra excitement as well (I know, there’s always something extra). A few of the Hudson team members stayed for one more week to do a medical clinic, plus we had a short-term intern, Betsi, who arrived the night the team left and stayed for three weeks.

Debbie "proving a point"
It was Betsi’s birthday, so we went to buy her a cake! This is Debbie proving to me that she doesn’t need a new organization system in her purse because her car keys are “right here!” She has things from her purse under both arms and her chin while also balancing the cake box. (If you’re wondering why I’m not helping, I was already holding her water bottle and mine, some snacks we bought from the bakery, and our notebooks.)
Betsi with her birthday cake
Happy Birthday Betsi! It’s a Peruvian tradition to crack an egg on the head of the (un)lucky birthday person, but Betsi made it clear that she wouldn’t be happy. I’m with her.

The medical clinic was great! It’s run by a husband and wife, a doctor and nurse duo, plus their daughter, who have been doing this for the last few years. At this point, they have ongoing relationships with some of the patients which is pretty cool. Often, when medical groups come in, they focus on the kids in the program, but this one is primarily for the parents, staff, and people connected to them. It’s a big blessing for the people in our community to be able to visit a doctor who really knows what he’s talking about! I could tell you dozens of stories about doctor-related headaches here. It’s hard to find a doctor you can trust, and sometimes, it’s hard to find a doctor at all! Once, one of the kids had a medical problem, and the staff had to take her here, there, and everywhere to find someone who would help her. I can’t imagine how frustrating it must be for that to be your ongoing reality.

I only popped in a few times during the week, but it was fun to see the clinic in action. People asked questions about whatever aches and pains were plaguing them, they gave out reading glasses to people who needed them, one of the moms brought in her 1-month-old baby for a checkup… It made me so happy that all of these people could see a doctor who really cares and knows his stuff.

Illuminated waves
Night ocean views in Lima
Googly-eyed head with grass hair growing out of the top
One of the younger classes made these little seed-heads. I’m pretty sure they’re essentially pantyhose stuffed with dirt and seeds. Once the “hair” started growing, they stopped looking like creepy potatoes and started looking kind of cute! And hilarious. Do you like this one’s hair tie?
Googly-eye head with a haircut
This one is a little disturbing… someone cut his hair and now he’s sitting on a bed of his own hair clippings. Eek.

In construction news, THINGS ARE HAPPENING! I still haven’t gotten used to the fact that the building looks more and more like an actual building each day… I’m still in “foundations” mode where I think that we’re going to move at a snail’s pace for the rest of forever, and we’ll never make it above ground. Silly me because like I said in my last post, we have walls! And now we have the beginnings of windows! And WE HAVE FLOORS! And they’re working on making it so that there are CEILINGS too!

I know, I know. You’re thinking, “Duh, Lara. You’re just listing all of the parts of a building. You knew that they were building a building, didn’t you?” YES, I DID. But seeing it come together right in front of me is a whole bunch of insanity. And now, take a gander at the pictures and please also be awed by the fact that what was once a hole in the ground is now actually starting to look like something that could be recognized as a building.

Module 1 with completed brick walls
Finished walls in Module 1!
Module 2 with new walls
More walls in Module 2! And you can see the wooden formwork for a concrete bench in front of the building
Wall and columns in Module 2
After they finished the brick for this wall, they poured the columns so that the entire wall/column structure is working together.
Brick wall with a column in the middle
Here’s one of the wall-integrated columns.
Window holes in Module 2
This is how they frame out the windows in a brick wall. They basically pour mini-columns on the sides and frame out the top and bottom with steel and concrete.
Module 2 with formwork around the mini-columns
These are the same windows, now with the formwork for the concrete.
Window hole with concrete surrounding it
One of the finished window frames on Module 1. I’m so excited about these windows! These classrooms are going to have way more natural light than the other rooms we have.
Module 2 walls
The bench has been poured! (See above the blue tarp) and you can see the window wall going up in the background
The top 2/3 of this wall is going to be exposed brick, and the bottom 1/3 is going to be covered. Can you see the difference? The brick pattern on top is different, and they clearly put a lot more effort into making sure it looks nice and neat.
Freshly poured concrete floor in Module 1
MODULE 1 FLOOR!!! It’s like a real room now! They were still in the process of pouring the back of the room in this picture.
Construction guys preparing concrete for the floors
The concrete mixing station. For big pours, they’ll call a concrete truck, but even for these floors, they mixed the concrete themselves using this concrete drum. Concrete, gravel, water, sand, repeat. Pour days are always VERY long, and I’m sure they’re exhausting.
Ground level view of the new floor
This is just the sub-floor, so there’s going to be another layer of concrete on top of this… but we have a floor!! Can you tell I’m excited?
Floors in Module 2
Floor in Module 2! There’s a floor inside the classroom, plus they poured the walkway outside.
Concrete floor in the future staircase
Future staircase! It’s cool to see everything starting to take shape.
Sticks holding up some planks
Next step: ceilings! This is the very beginning of the “scaffolding” they built to hold the ceiling up.
Framing out the beams
These horizontal pieces of wood are where the beams are going.
Rebar for the beams and the beginnings of the ceiling formwork
Look at the steel where the beams are! And those planks in between are going to help hold up the rest of the ceiling.
More rebar for the beams
Almost finished with the beams!
Sticks to support the ceiling
Stick forest. Jocelyn was laughing at their strategy for making the sticks the height they need to be… what do you think? Seems very stable…

There you have it! See? It’s like a real building now. Hopefully you’re not bored of all of these construction pictures because there are many more to come. I think the process is fascinating! And sometimes mildly terrifying, but mostly fascinating.