The last couple of weeks have been overwhelming, hence why I haven’t been posting recently. Last time, I wrote about trying to maintain a work-life balance. It wasn’t going very well then, and it hasn’t improved since. That’s why I’ve been missing in action recently. I could feel myself starting to fall apart, and I needed to cut something out in an attempt to give myself a chance to recover. I think it worked? Maybe? A little? But I’m still in the middle of a period of chaos, so we’ll see if I can make it out on the other side in one piece.
Let me try to catch you up on all of the happenings…
1. Our construction start date got pushed back again until May 13th. I know it sounds like we’re never actually going to start building, but this is the final final final start date. On May 20th, we have another team coming from the US, so if we don’t start before then, it’s really never going to happen. This is a good thing, though. We were so not going to be ready by the other date, partly because…
2. Our new structural engineer may be a miracle worker, but he’s still human and needs time to get everything done. I mentioned in my last post that we switched engineers because the first one wasn’t working out. Basically, they delivered a half-finished design, and a bunch of people found errors in their work that they refused to fix. Good, right? It was unfortunate to have to make a change in the middle of the project, but this new guy we’re working with really has it together. His design is SO much better, he meets deadlines and communicates well, and we’re actually confident that he knows what he’s talking about. Imagine that.
3. Two weeks ago was simultaneously the best and worst week because of the Easter vacation. We only worked Monday – Wednesday which would have been more fabulous if I didn’t need to fit 5 days of work into 3. It was stressful, to say the least, and by the time I went to sleep on Wednesday, I didn’t have much left in me… energy, patience, or brain functionality. So maybe it was good that it was only a three-day week.
4. For the holiday break (Thursday – Saturday), we went on a mini-vacation into the mountains! The pretty, green, not-in-the-middle-of-the-desert mountains! It was exactly the break I needed (until I got a reality check back at work on Monday). I can’t even explain to you how nice it was to be away from the compound. Everyone was so relaxed. The mountains were beautiful. The weather was cooler. We didn’t talk about work at all. I think we all needed a bit of an escape from reality. I’m going to write more about our trip in another post because I have lots of pretty pictures to share!
5. Last week was a mess. Our deadline for “finishing” our drawings is next Saturday, and yesterday we had a sort of pre-submission to prepare for a meeting this week to make final decisions about a few things that are currently up in the air. I feel overwhelmed. There are so many things left to do, and it seems like I keep getting surprised with more and more. Like maybe I asked a month ago if we wanted ‘x’ in the building, the answer was no, and last week, the answer became yes. I had a bit of a meltdown. It’s been worked out, though, and I’m praying for focus so that this can be a productive week. It needs to be.
6. The reason I said “finishing” in quotes in #5 is because we need to put together our drawings for pricing, but we haven’t had time to look at light fixtures yet. That means that I have maybe 20% confidence in my lighting layouts because how can I be sure about something that is based completely on speculation? At least construction happens from the ground up, so there’s some time to do research before they need to start installing pipes for the wiring and such. Still, it’s stressful to feel like I’m being pushed to make decisions without nearly enough information.
7. Even though actual construction hasn’t started, pre-construction has! This week kicked off some of the site preparation work. We had a front-end loader here on Thursday to put in a gravel driveway, and the guys are putting up a little building with a bathroom/shower and storage and changing areas for the construction workers. Legit construction companies make plans for this kind of thing – where materials will be located, where to put construction fencing, how pedestrians will be re-routed, etc. It might be okay to just wing it on a smaller project here, but this is going to be a big disruption to the programs no matter what. We want to minimize the impact as much as possible.
Okay, I think that’s all. This week is sure to be another one of chaos with the goal of making next week slightly more manageable… until construction starts the week after, and we’re right back to chaos! Hopefully that will be an exciting chaos, though, and not the type that makes me feel like I’m going to implode.